Cottonworks Mill Project

Holden mill Project

In conjunction with Recom & Halliday Meecham

April 30, 2021 Level 6/7 Programme and Apartment Phasing

Level 7
Benchmark - 15/11/21 to 22/12/21
Apartment 621, 623
Phase 1 - January 2022
Apartments: 610, 611, 612, 613, 614, 615, 616, 617, 618, 619, 620, 624, 625, 626, 627, 628, 629, 630, 631, 632, 633, 634
Phase 2 - February 2022
Apartments: 602, 603, 604, 605, 606, 607, 608, 609, 635, 636, 637, 638, 639, 640, 641, 642

Level 6
Benchmark - 15/11/21 to 22/12/21
Apartments: 621
Phase 1 - January 2022
Apartments: 618, 619, 620, 624, 625, 626, 627
Phase 2 - January 2022
Apartments: 614, 615, 616, 617, 628, 629, 630, 631
Phase 3 - February 2022
Apartments: 610, 611, 612, 613, 632, 633, 634, 635
Phase 4 - February 2022
Apartments: 606, 607, 608, 609, 636, 637, 638, 639
Phase 5 - March 2022
Apartments: 602, 603, 604, 605, 640, 641, 642

Please be aware, there will be four teams working concurrently throughout the project.

PROGRAMME DATES ARE SUBJECT TO CHANGE

Please be aware that no works will be taking place during the Christmas shutdown period from 24th December 2021 – 2nd January 2022

Phasing Plan – Please click here to view the phasing plan

Team A – Blue

Team B – Red

Team C – Yellow

Team D – Purple