Cottonworks Mill Project

Holden mill Project

In conjunction with Recom & Halliday Meecham

April 30, 2021 Level 6/7 Programme and Apartment Phasing

The cladding installation is now complete, the final installation of the verges and guttering at the North end of the building are underway along with snagging on all elevations.



Please be aware that in adverse weather conditions; heavy rain, frost and winds exceeding 20MPH works cannot take place on Level 6 and 7 for health and safety reasons which may affect the target completion dates listed below:

Gutter/Verge Installation
Level 7 - complete
Level 6 West - complete
Level 6 East - complete

Benchmark - Level 7
Apartment 621, 623 - Complete

Phase 1 Level 7 - 18/01/22-18/03/22
610, 611, 612, 613, 614, 615, 616, 617, 618, 619, 620, 624, 625, 626, 627, 628, 629, 630, 631, 632, 633, 634
Cladding complete - snagging and remediation underway

Level 6 and 7 West
623 to 628 - 21/02/22 to 18/03/22
629 to 631 - 07/03/22 to 23/03/22
632 to 634 - 21/03/22 to 01/04/22
635 to 637 - 31/03/22 to 14/04/22
638 to 640 - 13/04/22 to 29/04/22
641 to 642 - 28/04/22 to 27/05/22

Level 6 and 7 East
621 to 616 - 21/02/22 to 18/03/22
615 to 613 - 07/03/22 to 23/03/22
612 to 610 - 21/03/22 to 01/04/22
609 to 607 - 31/03/22 to 14/04/22
606 to 604 - 13/04/22 to 29/04/22
603 to 602 - 28/04/22 to 27/05/22

PROGRAMME DATES ARE SUBJECT TO CHANGE

Thank you for your patience.