Cottonworks Mill Project

Holden mill Project

In conjunction with Recom & Halliday Meecham

April 30, 2021 Please be aware the cladding replacement works are currently on hold due to a delay with the release of funding from the government.

Programme & Apartment Phasing

Please be aware, there will be three teams working concurrently throughout the project

PHASING IS SUBJECT TO CHANGE

Level 7
Phase 1
Apartments: 621, 623, 624, 625, 642
Phase 2
Apartments: 618, 619, 620, 621, 626, 627, 628, 629
Phase 3
Apartments: 614, 615, 616, 617, 630, 631, 632, 633
Phase 4
Apartments: 610, 611, 612, 613, 634, 635, 636, 637
Phase 5
Apartments: 606, 607, 608, 609, 638, 639, 640, 641
Phase 6
Apartments: 602, 603, 604, 605, 642

The cladding replacement works were due to begin in June 2020 and completed by the end of the year. However, there has been a delay with the release of funding from the government, therefore, to reduce any resultant additional costs, the contractor has been stood down until the funding is received.

We have been informed that the funding should be issued over the next couple of weeks but there is a possibility this could be delayed further which is out of our control.