Cottonworks Mill Project

Holden mill Project

In conjunction with Recom & Halliday Meecham

April 30, 2021 Level 2 Programme & Apartment Phasing

Level 2
Benchmark - 15/11/21- 17/12/21
Apartment 218 Gable
Phase 1 - 20/12/21-11/03/22


Phasing Plan – Please click here to view the phasing plan

Please be aware that no works will be taking place during the Christmas shutdown period from 24th December 2021 – 2nd January 2022

There will be four teams working concurrently throughout the project.

PROGRAMME DATES SUBJECT TO CHANGE