Cottonworks Mill Project

Holden mill Project

In conjunction with Recom & Halliday Meecham

April 30, 2021 Programme & Apartment Phasing

Please be aware, there will be three teams working concurrently throughout the project

PHASING IS SUBJECT TO CHANGE

Site Set Up: 26th April - 11th June

Level 2
Phase 1 (28th June - 30th July):
Apartments: 206, 207, 208, 209, 210
Phase 2 (2nd August - 20th August):
Apartments: 211, 212, 213, 214
Phase 3 (23rd August - 10th September):
Apartments: 215, 216, 217, 218
Phase 4 (13th September - 1st October):
Apartment: 218

Please be aware, all dates are subject to change.

Current apartments undergoing works: None

2 week lookahead:

Week 1: Site set up will continue, contractor cabins will be connected to water, electricity and drainage.

Week 2: Site set up will continue, scaffolding construction will begin for Level 2, near entrance B