Timpsons – New Training Facility
Wythenshaw, Manchester
RECOM Solutions was appointed to project manage the new Timpsons Training Facility in Wythenshawe, from RIBA Stage 1 through to completion.
Overview
Project Details
Recom Solutions undertook the Project Management of the new Training Facility in Wythenshawe, appointed at RIBA Stage 1. The various fit out projects undertaken were completed within a live office environment, which presented unique logistical issues throughout the builds.
Recom undertook refurbishment of the main office reception, IT space and warehouse staff offices.
Client
Timpsons – New Training Facility
Value
£4M
Completion
01 June 2019
Process
What We Did Differently
The complete refurbishment included:
- Mechanical and Electrical Design
- Full Design Management
- Full Mechanical and Electrical works
- Drylining and ceilings
- IT installations
- Decoration and wall finishes
- Flooring finishes throughout
- Joinery – Glulam Structure
- Tiling
- Kitchen installation
- Bespoke Furniture manufacture and install
- Handover and Commissioning
Outcomes
Key issues, managed by Recom Solutions
Programme and Sequencing Detailed design management and procurement to ensure the build was delivered in accordance with a tight budget.
Stakeholder Liaison Recom Solutions held daily meetings with the client to ensure the successful handover of the project whilst working in a live, sensitive environment.
Design development was required throughout the project, due to limited information provided by the Client.
Noisy and disruptive works were programmed out of office hours to limit disruption to Timpsons staff.
Accreditations