HOLDEN MILL PROJECT

7th FLOOR, WEST ELEVATION: TOTAL PROGRAMME 26WEEKS

LEVEL 7

West Elevation

Total Programme: 26 weeks (21st June – 17th December)

Phase 1 (21st June – 30th July): Apartment: 623, 624, 625, 642

Phase 2 (2nd August – 27th August): Apartments: 626, 627, 628, 629

Phase 3 (30th August – 24th September): Apartments: 630, 631, 632, 633

Phase 4 (27th September – 22nd October): Apartments: 634, 635, 636, 637

Phase 5 (25th October – 19th November): Apartments: 638, 639, 640, 641

Phase 6 (22nd November – 17th December): Apartments: 642